Automation & SCADA
- Client Name: MES, Bangalore
- Manual Operation Due to plant air demand variation multiple centrifugal air compressors were operating at an unequal load pattern Inefficient operation due to imbalanced equipment loading and excess air blow-off situations.
- Automation Solution PLC-based Energy Efficient Control system with an equal load sharing logic resulted in reduced cost of maintenance, managed preventive maintenance schedule, higher Reliability.
- Project Value: INR 0.11 Crores (ROI approx. 9 to 12 months)
- Manual Operation
- Combined various Utility equipment data not available in one place for MIS purposes.
- Need to refer multiple systems (compressors, dryers, chillers, pumps, motors, etc.) to assess health, maintenance schedules, and efficiency which resulted in reliability and efficiency issues.
- Automation Solution
- Collected all data for all equipment at one central location using logic from OEMs and built logic to ensure the safety of the equipment.
- Designed SCADA system with real-time efficiency and health of the utility system over and above Daily, Weekly, Monthly, and Annual reports covering all important parameters of all utility equipment.
- Project Value: INR 0.20 Crores (ROI approx. 12 to 15 months)
- Client Name: Maruti Suzuki, Rohtak (R&D Centre) + Hero Motorcycles, Jaipur
- Manual Operation Due to plant air demand variation multiple centrifugal air compressors were operating at an unequal load pattern Inefficient operation due to imbalanced equipment loading and excess air blow-off situations.
- Automation Solution
- Designed a complete system with the supervisory controller to integrate all the equipment of HVAC.
- Monitor and control the entire HVAC system from a single point.
- Customized reports for energy calculations
- Controller runs systems based on performance and sequencing.
- Project Value: INR 0.25 Crores
- Client Name: Ultra Denim, Surat
- Manual Operation
- Manual Data Logging: Logbook not accurate, discipline issues, cost of manpower, stationary, inventory, record keeping etc.
- Interpretation issues with different shift operators/manpower
- Alarms missed/ignored to take preventive measures/maintenance.
- Reporting was mostly on Break Downs or Purchase Requisitions!
- Automation Solution
- Data Logging of values with time stamping up to one year in SCADA
- System provides historical trends, sensitizes and escalates alarms, prepares reports, and provides preventive maintenance schedules!
- Customized reports for energy calculations
- Controller runs systems based on performance and sequencing.
- Project Value: INR 0.11 Crores (ROI approx. 9 to 12 months)